The intake jetty at Hunterston Nuclear Power Station in North Ayrshire, Scotland was in need of concrete repairs to the soffit.
Previous attempts to repair the soffit using conventional scaffolding had been unsuccessful as stormy weather had demolished the scaffolding.
Apollo were then approached to create a workable solution. We provided a number of 9 x 7.8 metre platforms that could be lowered into a working position and then raised during rough seas combined with the ability for quick removal should a storm be forecast.