PD Ports Quayside Repair


The PD Ports facility in Teeside has a 512 metre long quayside where container ships load and unload.

 

The concrete beams under the quayside were in desperate need of repair.

Apollo’s scope was to provide access to four work packages at one time and reposition to the remaining six when the works were complete.

 

Due to tides, the access would be underwater twice each day so we had to think out of the box.

We chose a method using wire ropes called a catenary wire system with stagings which allowed water to pass through.

 

Both our client and PD Ports were highly delighted with the solution we provided and the increased productivity it offered to the job.

Project Scope

Repair to concrete beams under quayside.


Apollo Scope

Access to four work packages required at one time.


Additional Points

Access underwater twice each day, meant incorporating a catenary wire system.


If this access solution meets the needs of your project, contact us to see how Apollo can help you.

Project Image Gallery

  • PD Ports Quayside Repair - Image 1
  • PD Ports Quayside Repair - Image 2
  • PD Ports Quayside Repair - Image 3
  • PD Ports Quayside Repair - Image 4
  • PD Ports Quayside Repair - Image 5
  • PD Ports Quayside Repair - Image 6
  • PD Ports Quayside Repair - Image 7
  • PD Ports Quayside Repair - Image 8
  • PD Ports Quayside Repair - Image 9
PD Ports Quayside Repair - Image 1 PD Ports Quayside Repair - Image 2 PD Ports Quayside Repair - Image 3 PD Ports Quayside Repair - Image 4 PD Ports Quayside Repair - Image 5 PD Ports Quayside Repair - Image 6 PD Ports Quayside Repair - Image 7 PD Ports Quayside Repair - Image 8 PD Ports Quayside Repair - Image 9
  • Apollo Scaffold Services
  • Apollo LPG repairs and servicing